Schedule
1. Phase 1: Preliminary studies
April 2007
Consultation assessment
October 2007
Designation of project managementœ
2. Phase 2: Pre-works
May 29
Choice of design
Summer 2008
Validation of preliminary draft
Winter 2009
Public Utility Inquiry
3. Phase 3: Construction work
July 2009
Start of work to divert grids and networks
March 2010
Start of construction work for the light rail roadbed
June 2010
First stone of the depot buildings laid.
June 2010
First rail weld
4. Phase 4: Trials
Late 2011
First train will run on the line
5. Phase 5: Inauguration
Mid-2012
Inauguration and commissioning